The Road to Redevelopment

Date 12 Jul, 2023

Click the image for the full size.

Timeline

In 2017, community engagement, redevelopment and capital campaign feasibility studies set the stage for an incredibly ambitious project— the redevelopment of our site at 320 E Hastings. Five years later, site work got underway

2022

April– Street Use and Salvage & Abatement permits are received, clearing the way for preliminary work to begin on site.

May– Final ceremonies are held at 320 East Hastings. FIRST’s services are relocated and construction fences are put up.

JuneHazmat work begins on site. BC Housing issues preliminary project approval (PPA).

July– Hazmat work is extended due to the discovery of high amounts of asbestos on site.

December– The City approves Building Permit Phase I and our capital campaign hits $27.3M.

2023

March– Cost increases are shared at our AGM. FIRST’s fundraising goal is raised to $37M.

May– Hazmat work completes. The City of Vancouver issues our Demolition Permit and demolition begins. BC Housing confirms our Final Project Approval (FPA)

July– Building Permit Phase II is approved and excavation and shoring work (groundbreaking!) begin on site.

SeptemberBelow-grade construction begins with work on the foundation and parkade level of the building.

DecemberAbove-grade construction begins, with work on the superstructure and finishes.

2025

Winter– Twenty-four months after the start of below-grade construction, the building is complete!

Please note: this timeline is approximate, based on the current construction schedule.

Share to

Latest news

15 Nov, 2024
FIRST UNITED’s Downtown Eastside Redevelopment Project Launches New Art Initiative and Confirms $1 Million in Support from Audain Foundation
read more
6 Nov, 2024
Why we kept returning to Oppenheimer Park
read more
12 Jul, 2024
This Place for Displaced
read more